Short answer: a final location survey (FLS) is the last and most detailed survey before a railway project is sanctioned. It fixes the centre line, curves and gradients, and produces detailed plans, longitudinal and cross-sections, bridge and yard plans and the data for the detailed estimate[1][2]. A drone or aerial LiDAR survey, tied to DGPS control and bench marks, supplies most of the topography; centre-line pegging, pillars, soil investigation and river studies remain ground work.
Where the FLS sits in railway project planning
The Indian Railways Code for the Engineering Department links each survey stage to a report. A reconnaissance survey supports a feasibility study, a Preliminary Engineering-cum-Traffic Survey (PETS) leads to a Techno-Economic Survey Report, and a final location survey leads to the Project Report, which carries the detailed estimate and the abstract cost of the project[2].
| Stage | Purpose | Typical survey work | Report |
|---|---|---|---|
| Reconnaissance | Is the project worth investigating further? | Maps, imagery, site visits, waterway at major crossings[1] | Feasibility report[2] |
| PETS / traffic study | Compare routes, test viability, estimate cost closely | Route traverses; photogrammetry where suitable photographs exist[1]; traffic study | Techno-Economic Survey Report[2] |
| Final location survey | Fix the alignment and prepare plans for construction and sanction | Centre line, levels, cross-sections, bridges, yards, land, soil | Project Report with detailed estimate[2] |
| Detailed estimate and DPR | Sanction of the project and award of works | Quantities and costs worked out from the FLS drawings | DPR in the Railway Board format[3] |
The order matters. In 2025 the Railway Board told zonal railways to get the traffic study done before going ahead with a final location survey, so that money is not spent surveying a line that is not viable[5]. Its revised FLS rates now include the traffic study within the FLS cost[4]. Under the Railway Board's arrangements for empanelled consultants, the consultant first does the traffic study to test viability, then goes on to the FLS and the DPR[3].
FLS and DPR work covers new lines, doubling and multi-tracking, gauge conversion and yard remodelling[3]. Yard remodelling overlaps with the Engineering Scale Plan (ESP), which shows an existing yard to scale before changes are designed.
What the Engineering Code asks an FLS to deliver
Chapter IV of the Engineering Code sets out the final location survey in detail. The survey should be comprehensive enough to give the information needed for the detailed plans and sections and for an accurate estimate of cost, and it should secure the most economical alignment[1]. The main requirements are below.
Alignment, curves and gradients
- Centre line: measured in chains of 20 metres, with pegs at every chain and larger pegs at every 100 metres[1].
- Permanent marks: masonry pillars at tangent points and at intervals along the line, so the alignment can be set out again at construction[1].
- Curves: defined by degree and radius, with transition curves where the curvature changes; gradients are expressed per 100 metres and compensated for curvature[1].
- Levels: bench marks at intervals of not more than one kilometre and at the sites of important bridges, referred to mean sea level[1].
Plans and sections
The Code lists the set of plans and sections a project should have: a general map, an index map, an index plan and section, detailed plans and sections, plans and cross-sections, station yard plans, drawings of structures and plans of junction arrangements[1]. Some of the scales it gives:
| Drawing | Scale in the Code | What it shows |
|---|---|---|
| Index plan and section | 0.5 km to 1 cm horizontal, 10 m to 1 cm vertical | The whole line, with important bridges, rivers and spans |
| Detailed plans and sections (L-section) | 50 m to 1 cm horizontal, 5 m to 1 cm vertical | All features within 100 m each side of the centre line, including village boundaries; ground and formation levels |
| River plans and cross-sections | Plan at 50 m to 1 cm; sections at 5 m to 1 cm | Rivers needing a waterway of 110 sq. metres or more |
| Station yard and junction plans | 10 m to 1 cm | Stations needing special design and junction layouts |
All scales above are from Chapter IV of the Engineering Code[1]. The longitudinal section carries two sets of levels, the ground and the formation, and cross-sections are referenced on it[1]. Larger scales may be used in difficult country.
Bridges, culverts, soil and land
Every waterway crossing needs a site study: catchment, flood levels, scour and the size of opening. Large bridges need skeleton drawings for the estimate, and the Code asks for bunds and irrigation works on the route to be investigated, along with any diversion they need[1]. In hilly country a geological investigation is needed, and soil samples are taken systematically along the route and at borrow areas[1]. Land plans, drawn over village and revenue maps, show the land to be acquired and the boundaries it crosses; the detailed plan already shows village land boundaries within 100 metres of the centre line[1].
How drone photogrammetry and LiDAR fit an FLS
The Code was written for theodolite traverses and levelling, but it already allowed photogrammetric techniques for the preliminary survey where suitable aerial photographs were available[1]. Current Railway Board instructions for FLS and DPR consultants go further: they say technological tools such as LiDAR survey and satellite imagery on the BISAG portal should be used for survey work, that the alignment should be planned on the BISAG platform, and that a drone project video should be made where required[3].
High-speed rail shows the method at scale. NHSRCL used helicopter-mounted aerial LiDAR, combining laser data, GPS data, flight parameters and photographs, to map the Delhi–Varanasi corridor as a 3D topographic map 50 metres either side of the proposed alignment[6]. On the Mumbai–Ahmedabad corridor the aerial LiDAR ground survey took 12 weeks, against 10 to 12 months by traditional methods, and fed the design of the vertical and horizontal alignment, structures, stations, land requirement and affected plots[7]. Drones and helicopters were also reported in use for the FLS of the Sambalpur–Gopalpur line in Odisha in 2020[8].
For a conventional line, a drone does the same job over a narrower strip, with lighter logistics than a helicopter. The workflow is:
- Control first. A DGPS control network along the corridor, tied to the project datum and to bench marks levelled from mean sea level.
- Flight. Photogrammetry for open country and built-up areas; drone LiDAR where vegetation, cuttings or hill slopes hide the ground. Many corridors use both.
- Processing. Orthomosaic, digital terrain model and contours, plus a classified point cloud from LiDAR.
- Engineering extraction. Longitudinal section along the chosen centre line, cross-sections at the required interval, feature mapping within the corridor and land plans over revenue maps.
- Ground work that stays on the ground. Pegging and pillars, river and bridge site studies, soil and geological investigation, and checks of features the aerial data cannot see.
The main gain is that the alignment can be moved on the terrain model without resurveying. Several options can be tested, curves and gradients adjusted, and the sections regenerated before anything is pegged. The comparison with ground methods is covered in drone survey vs DGPS and total station.
Accuracy and ground control
An FLS is only as good as its control. On a linear corridor, ground control points are spread along the full length and alternate on both sides of the alignment, with a pair at each end, so the model does not bend or tilt along its length. Checkpoints are measured the same way but held out of processing, so the accuracy can be proved.
- Datum: plan coordinates in the project system, and heights as orthometric heights tied to bench marks, not raw GNSS ellipsoidal heights.
- Chainage: every section, plan and point in the data should carry chainage, so the drawings, the pegs on the ground and the estimate agree.
- Accuracy report: residuals at independent checkpoints reported as RMSE in X, Y and Z.
- Vertical accuracy matters most. Earthwork quantities come from the difference between ground and formation levels, so a small bias in the terrain model becomes a large error in the estimate.
How GSD, GCP spacing and RTK or PPK positioning set the achievable accuracy is explained in how accurate is a drone survey.
Deliverables and file formats
The output of a drone or LiDAR survey for an FLS should be ready for the alignment designer and the estimator, not only a map. A typical set:
| Deliverable | Format | Used for |
|---|---|---|
| Orthomosaic of the corridor | GeoTIFF | Base for plans, land plans and route review |
| Terrain model and contours | GeoTIFF, DWG | Alignment design, earthwork, drainage |
| Point cloud | LAS / LAZ | Ground under vegetation, cuttings, structures |
| Detailed plan, L-section and cross-sections | DWG | FLS drawings at the Code scales, quantities |
| Bridge and culvert site plans | DWG | Waterway design, skeleton drawings |
| Land plans and GIS layers | SHP, DWG | Land acquisition, utilities, encroachments |
| Control and accuracy report | PDF, CSV | Proof of accuracy; setting out at construction |
What each of these products is, and how it differs from the others, is covered in drone survey deliverables explained.
Common pitfalls
- Too narrow a corridor. If the strip only covers the first alignment, every shift needs a new flight. Fly wide enough for realignments and for the 100 metres each side the Code's detailed plan needs[1], more where yards or junctions will be built.
- Photogrammetry under trees. A photogrammetric model maps the canopy, not the ground. Use LiDAR or ground survey in forests, orchards and overgrown cuttings, or the L-section will be wrong; see LiDAR vs photogrammetry.
- Mixed height systems. Ellipsoidal GNSS heights mixed with levelled bench marks give formation levels that do not match the ground at construction.
- Water and river beds. Neither LiDAR nor photographs see through water. River cross-sections, bed levels and flood levels need ground survey, bathymetry and local records.
- No independent checkpoints. Without them the accuracy of the terrain model is unproven, and the earthwork estimate inherits the doubt.
- Hidden services. Buried cables, pipelines and drains do not appear in aerial data. Utility records and ground checks are still needed for the shifting estimate[3].
- Land plans on the wrong base. Revenue maps must be fitted carefully to the orthomosaic; a poor fit puts the land boundary in the wrong field.
How DATA PKT works on railway surveys
DATA PKT has prepared more than 60 yard plans, Engineering Scale Plans and drainage plans for railway divisions from drone survey with DGPS ground control; read the railway yard and drainage plans case study. Our in-house GIS team turns the survey data into CAD drawings and GIS layers. See railway and metro surveys, ESP and DPR surveys and railway drone inspection.
Sources
- Indian Railways Code for the Engineering Department, Chapter IV: Reconnaissance, Preliminary and Final Location Surveys (paras 401–474). indianrailways.gov.in
- Indian Railways Code for the Engineering Department, Chapter V: Engineering Surveys, reports and estimates (paras 501, 545, 553–555). indianrailways.gov.in
- Railway Board letter No. 2022/W-I/Genl./DPR Proforma, October 2024: empanelled list of consultants for conducting FLS and preparing DPRs (use of LiDAR survey, satellite imagery and the BISAG portal; drone project video; traffic study first). indianrailways.gov.in
- Railway Board letter to all Indian Railways, 28 July 2025: revision of rates for Final Location Surveys (traffic study included in the FLS cost). indianrailways.gov.in
- ThePrint (PTI), 6 October 2025: Railways asks zones to conduct traffic study before final survey to prevent wasteful expenditure. theprint.in
- Press Information Bureau, Ministry of Railways, 10 January 2021: LiDAR (aerial ground) survey for the Delhi–Varanasi high speed rail corridor begins. pib.gov.in
- NHSRCL press release: NHSRCL adopts aerial LiDAR survey technique to conduct the ground survey for the Delhi–Varanasi high speed rail corridor. nhsrcl.in
- OdishaBytes, 10 November 2020: For the first time, drones and helicopters to make location survey for new train line project in Odisha. odishabytes.com