Home / Case studies / Slope stability, Assam

Case study · Landslide and slope stability

Slope stability investigation of a 66 km road corridor in Assam

For a private client, DATA PKT investigated the road-side slopes of a ~66 km hill road corridor in Assam with drone LiDAR, seismic refraction tomography and geological mapping, and delivered a stability report that ranked every stretch and gave the inputs to design its protection.

LocationRoad corridor in Assam, Northeast India
LengthAbout 66 km of road-side cut and fill slopes
ClientPrivate client (name withheld)
DurationAbout 9 weeks, with about 3 weeks in the field

In short: we flew drone LiDAR along the full ~66 km corridor, shot 66 seismic refraction profiles (about one per kilometre), mapped the geology in detail at 7 critical locations (2.12 km), and combined all three in one ground model. The stability analysis gave a factor of safety for each critical section in dry, monsoon-saturated and earthquake conditions, and every stretch was ranked by hazard with remedial measures and protection design inputs.

The challenge

The client needed to know which slopes along the corridor were most likely to fail, how, and what it would take to hold them, so that slope stabilisation and rockfall protection could be selected and dimensioned for the critical stretches. The corridor is a hard place to answer that question:

  • Very heavy monsoon rain, of the order of 2,500–3,500 mm a year, which saturates the slopes
  • Seismic Zone V under IS 1893, the highest seismic zone in India
  • Dense vegetation covering the slopes, hiding the ground from photographs
  • Soft alluvial soils and weathered sedimentary rock in the cut sections
  • Failures mainly through rain-induced shallow slides, erosion and toe scour, and structurally controlled rock failures
  • A narrow, live road: every field crew had to work around traffic

Scope of work

ItemQuantityWhat it involved
MobilisationTeam of 8 with all equipmentGurugram to Assam and back
Seismic refraction tomography (SRT)66 profiles (~1 per km)24-channel profiles, 3–5 m geophone spacing, 9 shots per spread, tomographic inversion and interpretation
Drone LiDAR survey~66 km, ~100 m wide corridorRTK/PPK drone LiDAR with DGPS control; classified point cloud, DTM/DSM, contours, orthophoto, cross-sections
Geological mapping7 locations, 2.12 kmEngineering geological mapping, discontinuity survey, field strength tests, RMR, GSI, SMR, Hoek–Brown strength
Analysis and reportCorridor-wideIntegrated interpretation, slope stability analysis, hazard ranking, remedial measures, draft and final report
0 km10 km20 km30 km40 km50 km60 kmG1G2G3G4G5G6G7 Drone LiDAR corridor (~100 m wide, full length) SRT profile (~1 per km, 66) Geological mapping (7 sites)
How the investigation covered the corridor: LiDAR along the full length, a seismic profile about every kilometre, and detailed geology at the seven most critical stretches (G1–G7). Distances are relative.

Our approach: three data sets, one ground model

No single method can characterise a slope. We planned three independent investigations, each answering its own question, and brought them together for the analysis:

  • Drone LiDAR showed what the ground surface looks like: slope height and angle, benches, cracks, scarps, drainage paths and changes at the road edge, under the vegetation.
  • Seismic refraction showed what lies below: the thickness of loose cover, the depth to weathered and fresh rock, and low-velocity zones that are weak or saturated.
  • Geological mapping showed how the material behaves: rock mass quality, joint orientations, possible failure mechanisms and shear strength.
  • The stability analysis put the three together: geometry from LiDAR, layering from SRT and strength from geology gave a factor of safety for each critical section.
Desk study · alignment data · drone permission · DGPS control networkDRONE LiDARthe surfaceSEISMIC REFRACTIONwhat lies belowGEOLOGICAL MAPPINGhow the material behavesDTM, contours, sectionsslope angle, scarps, 3DP-wave velocity sectionssoil thickness, rock depthRMR, GSI, SMR, jointsstrength c' and φ'Integrated ground modelgeometry + layering + strengthSlope stability analysisfactor of safety: dry, saturated, earthquakeHazard zonation · priority list · protection design inputs
The integrated workflow, from mobilisation and DGPS control to the hazard map and protection design inputs.

Seismic profiles were placed where they gave the most information: high cuts and embankments, visible distress, scour-prone sections beside water, and the seven geology locations. Their exact positions were fixed after reconnaissance and a quick-look LiDAR model, and every profile was surveyed by DGPS so the tomograms plot directly on the LiDAR cross-sections.

Road Ground surfacedrone LiDAR Soil / loose coverSRT: low velocity Weathered rockSRT: medium velocity Jointsgeological mapping Fresh rockSRT: high velocity Possible slip surface
On each critical section, the LiDAR surface, the SRT layering and the mapped joints define the slip surfaces checked in the stability analysis.

Methods and specifications

ComponentMethod and key specifications
DGPS controlStatic control pillars about every 7–8 km tied to Survey of India / CORS; WGS 84 / UTM; about 70 ground control points and at least 30 independent check points for the LiDAR
Drone LiDARRTK/PPK survey-grade drone LiDAR; 60–80 m above ground; 3 flight lines over the ~100 m corridor; at least 100 points per m²; vertical accuracy target of 5 cm RMSE (ASPRS 2023); multiple returns for a bare-earth DTM under vegetation
Seismic refraction24-channel seismograph; 10–14 Hz geophones at 3–5 m; 9 shots per spread with a stacked 8 kg hammer source; about 20–30 m investigation depth; tomographic inversion with RMS misfit under 5%
Geological mappingMapping at 1:500 to 1:1,000; scanline and window discontinuity surveys (IS 11315); Schmidt hammer and point-load tests (IS 8764); RMR (IS 13365), SMR (Romana), GSI (Hoek–Marinos); kinematic analysis on stereonets
Strength parametersGeneralised Hoek–Brown (2002) with equivalent Mohr–Coulomb c′ and φ′ over the slope stress range; Barton–Bandis for joints
Stability analysisLimit equilibrium (Bishop, Spencer, Morgenstern–Price) for soil and rock-mass slopes; planar and wedge checks for rock; static, saturated and pseudo-static seismic cases (IS 1893 Zone V)

How each stream was processed

  1. LiDAR: raw scans and GNSS/IMU data → PPK trajectory from the base station → point cloud and strip adjustment → check against ground control and classification → DTM, DSM and contours → sections, slope maps, 3D models and KMZ.
  2. Seismic refraction: SEG-2 shot records → geometry and elevations from LiDAR → first-break picking → delay-time starting model → tomographic inversion → velocity section and interpretation.
  3. Geology: field sheets and photographs → discontinuity database → stereonets and kinematics → RMR, SMR and GSI → Hoek–Brown c′ and φ′ → stability input parameters.

Execution and schedule

The work took about nine weeks from the work order. The field window was about three weeks, with the LiDAR, geology and seismic crews working in parallel in the post-monsoon dry season.

W1W2W3W4W5W6W7W8W9Field window (~3 weeks)Kick-off, data, drone permissionMobilisation, reconnaissance, DGPS controlDrone LiDAR, 66 kmGeological mapping, 7 sitesSeismic refraction, 66 profilesLiDAR processing and deliverablesSRT inversion and interpretationRMR / GSI / SMR, c' and φ'Stability analysis, hazard zonationDraft report and presentationFinal report and data hand-over
Nine-week schedule: field work in weeks 2–4, processing and analysis in weeks 4–7, draft and final report by week 9.

A typical field day ran from a 06:30 toolbox talk (safety, traffic, weather and equipment check), through field work by three crews from 07:00 to 16:30 (the LiDAR crew flew in the calm morning air; the seismic crew shot in gaps in the traffic), to data download, dual backup and quality checks in the evening. The client received a daily progress report: chainage covered, profiles done, issues and the next day's plan.

The team

RolePeopleResponsibilities
Project manager / senior geotechnical engineer1Planning, client liaison, QA/QC, safety, review of the stability analysis
Geophysicist and technician2SRT design, acquisition, field QC, inversion and interpretation
Senior engineering geologist and assistant2Mapping, discontinuity survey, field tests, RMR/GSI/SMR, strength
DGCA-certified drone pilot and co-pilot / data manager2Mission planning, LiDAR flights, data download and backup
DGPS surveyor1Control network, ground control, SRT and geology positioning
Office team, Gurugram5LiDAR processing, GIS/CAD drawings, geophysical and geotechnical analysis, report

Quality assurance

ActivityChecks
DGPSClosure of the static network; repeat observations on 10% of control points; RMS under 2 cm; checks against known benchmarks
LiDARBoresight calibration; strip-overlap difference under 3 cm; independent check points (ASPRS); visual QC of classification
Seismic refractionDaily line and geophone tests; reciprocal-time check within ±1 ms; repeat of noisy shots; RMS misfit under 5%; second-person review of picks
GeologyCompass declination correction; at least 10 point-load tests per unit; RMR/GSI/SMR assessed independently by two geologists
Analysis and reportModel checked by hand calculation on one section; internal peer review by a senior engineer; document control and revision log
DataChainage-based file naming; dual backup (SSD and cloud) every day; master data register

Safety and environment

  • Roadside work-zone traffic management to IRC:SP:55: cones, signboards, flagmen and reflective jackets at every seismic spread and drone take-off point
  • Drone operations under the Drone Rules, 2021 with Digital Sky permissions; no flying in rain, wind over 10 m/s, poor visibility or over crowds
  • Rock-face mapping only after a check for loose blocks; helmets at all times; an observer watching for rockfall; no climbing without rope access
  • Hammer-source safety: gloves, goggles, ear protection and a clearance zone
  • No tree felling; vegetation cleared by hand only along seismic lines; all waste taken back

What we delivered

ComponentDeliverablesFormats
Seismic refraction (66 profiles)Field data and logs; location map; first-break picks; P-wave velocity tomogram with interpretation for each profile; depth to competent strata; weak-zone identification; engineering parameters; ray coverage and RMS errorSEG-2, XLSX, PDF, DWG, KMZ
Drone LiDAR (~66 km)Classified point cloud; DTM and DSM; 0.5 m contours; orthophoto; slope-angle and aspect maps; longitudinal profile; cross-sections (20 m in critical stretches, 50 m elsewhere); 3D models of critical stretches; accuracy reportLAS/LAZ, GeoTIFF, DWG/DXF, SHP, OBJ, KMZ, PDF
Geological mapping (7 locations)Lithology and structural maps; discontinuity database; stereonets and kinematic analysis; plans and sections; RMR, GSI and SMR; c′ and φ′; field test results; geotagged photo logPDF, DWG, XLSX, Dips
DGPS controlControl station descriptions, coordinate list, network adjustment report, ground control and check-point listPDF, XLSX, CSV
ReportIntegrated interpretation; stability analysis (static, saturated, seismic); hazard zonation (Low / Medium / High / Critical); priority list; stretch-wise remedial measures and protection design inputsPDF and hard copies, all data on drive

How the results feed slope protection design

The investigation was scoped so that its outputs could be used directly to select and dimension flexible high-tensile steel protection systems:

Design needWhy it mattersWhere it came from
Slope geometry: inclination, height, length, surface irregularityMesh and anchor layout, system choice, quantitiesLiDAR DTM, 0.5 m contours, slope-angle map, sections, 3D models
Thickness of the unstable layer and depth to competent strataSoil nail and anchor length, bond zoneSRT velocity tomograms, cross-checked with geology
Shear strength (c′, φ′) and unit weightDimensioning and stability checksHoek–Brown from GSI and field strength; SRT correlations
Rock mass structure, joint sets, block size, failure mechanismMesh, cable net or barrier; anchor patternDiscontinuity survey, stereonets, kinematics, RMR / SMR / GSI
Rockfall source zones and fall-line profilesRockfall trajectory, barrier location and energy classGeological mapping of sources; LiDAR profiles; orthophoto
Groundwater and seepageDrainage alongside the protection systemSeepage mapping; saturated stability case
Where to act firstPrioritising protection works over 66 kmStretch-wise hazard ranking, factor of safety and priority list

Why it worked

  • One team, three disciplines: survey, geophysics and geology planned together and positioned on the same DGPS control, so every data set lines up.
  • LiDAR first, then the ground: a quick-look LiDAR model guided where the seismic lines went, putting effort where the risk was.
  • Built for the design that follows: every deliverable was chosen for the protection design it feeds, not for its own sake.
  • Corridor scale, short field window: parallel crews kept about 66 km of field work to about three weeks.

Planning slope protection on a hill road, railway or project site? See our landslide and slope stability service.

Send us the site KML or chainage and the outputs you need. We reply with a scope and quote.

Send an enquiry WhatsApp +91 8448559100

Frequently asked questions

What did DATA PKT do on the Assam corridor?

We investigated the road-side cut and fill slopes along about 66 km of road in Assam: a drone LiDAR survey of the full corridor, 66 seismic refraction tomography profiles (about one per kilometre), detailed geological mapping at 7 critical locations totalling 2.12 km, and a slope stability analysis with stretch-wise hazard ranking and remedial recommendations.

Why were three methods combined?

Each answers a different question. LiDAR shows the shape of the slope, seismic refraction shows what lies below the surface, and geological mapping shows how the material behaves. Combined in one ground model, they give a factor of safety for each critical section that none of them could give alone.

How long did the investigation take?

About nine weeks from the work order to the final report, with about three weeks in the field. The LiDAR, seismic and geology crews worked in parallel to keep the field window short.

Why is this corridor difficult?

The region gets very heavy monsoon rain, lies in seismic Zone V under IS 1893, and has dense vegetation, soft alluvial soils and weathered sedimentary rock in the cuts. Slopes fail mainly through rain-induced shallow slides, erosion and toe scour, and failures controlled by rock joints.

How were the results used?

The report gave the slope geometry, the thickness of unstable layers, shear strength parameters and failure mechanisms needed to select and dimension flexible high-tensile steel protection systems such as soil-nailed mesh, rockfall drapes and barriers, together with a priority list of where to act first.